1.       Which phase has deliverables such as Project Charter, Project Management Plan creation etc.
(a)     Project Preparation           
(b)     Business Blueprint
(c)     Realization          
(d)     Final Preparation

2.       Which phase has deliverables such as -As-Is Process Documentation, Proof-Of-Concept on System, List of FRICE components, Business Blueprint Document etc.
(a)     Project Preparation,
(b)     Business Blueprint
(c)     Realization
(d)     Final Preparation

3.       End User Training is provided in the phase
(a)     Realization
(b)     Final Preparation
(c)     Production Cutover
(d)     Run

4.       Production Support to the end users is provided in the phase
(a)     Realization
(b)     Final Preparation
(c)     Production Cutover
(d)     Run

5.       In which Phase and stream, are all the following activities conducted: Decide a Blueprint Approach, Create Value Realization Roadmap, Perform Business Objects Modeling, Create Business Solution Design, Perform Solution Transformation and Design
(a) Business Process Management Work Stream in Business Blueprint Phase      
(b) Organizational Change Management work stream in Business Blueprint Phase
(c) Project Management Work stream in Business Blueprint Phase
(d) Business Process Management Work stream in Project Preparation Phase

6.       Business Processes can be designed using which of the following options:
(a) Modeling tools (ARIS)           
(b) SAP Solution Manager         
(c) None
(d) Both


7.       In Business Blue Print Phase and Business Process Management work stream, the  following activities are performed as a work package / activity group: List Core Configuration Settings along with configuration objects for each function (such as FI, CO, MM) as relevant to the Business Processes, Generate models and specifications for developing Composite applications, Prepare list of Solution Gaps and FRICEW Objects to be developed, List of Third-Party Solutions required and the resulting integration requirements.
What is the name of the work package or activity group?
(a) Decide Blueprint Approach    
(b) Create Value realization roadmap      
(c) Business Objects Modeling   
(d) Solution Transformation Design

     
8.       In …………… Phase  the Production support readiness Work stream is used to support the solution in production, functionally and technically
(a) Final Preparation      
(b) Realization
(c) Go Live Support       
(d) Run

9.       In Go Live Support Phase, the Project Management Work Stream is used to review project management plans leading to conclusion of project-oriented activities for the respective project scope.
(a) Project Management            
(b) Production Cutover
(c) Product Support       
(d) Integrated Solution Management

10.   In …… Phase, the Organizational Change Management Work Stream is used to identify items required to ensure acceptance of the solution and document lessons learned from the project.
(a) Final Preparation      
(b) Realization
(c) Go Live Support       
(d) Run

11.   In ……  Phase, the End-user support Work stream is used to determine how incident management can be used to support business users and implement it
(a) Final Preparation      
(b) Realization
(c) Go Live Support       
(d) Run


12.   SAP Solution Manager can be accessed through which of the following UI options:
(a) SAP GUI     
(b) SAP NetWeaver Business Client       
(c) Web Browsers like MS Internet Explorer        
(d) All

13.   Which of the following is a Standard Role of Incident Management Work Center:
(a) Reporter      
(b) Processor    
(c) Administrator           
(d) All

14.   Which of the following work centers provide functionality of eCATT and Business Process Change Analyzer?
(a) Change Management work center      
(b) Test Management Work Center         
(c) SAP Engagement and Delivery Work Center   
(d) Technical Administration Work Center

15.   ............ also referred as Applications, represent the various application components in SAP such as Materials Management: Inventory Management/Phys.Inventory (MM_B), MM: Material Requirements Planning (MM_D), Materials Management: Purchasing (MM_E), Materials Management: Master Data (MM_G) etc
(a) Object classes         
(b) authorization classes
(c) authorization objects
(d) none

16.   SAP_ALL, SAP_NEW are examples of .......
(a) Standard SAP Profiles          
(b) Manually Created Profile
(c) Generated Profile     
(d) All

17.   Z_SD_Admin, Y_MMIM_Admin are examples of .......
(a) Standard SAP Profiles          
(b) Manually Created Profile
(c) Generated Profile
(d) All

18.   .......... is the SAP super user at the application level in SAP Standard clients 000, 001 and 066
(a) SAP*          
(b) DDIC           
(c) EARLYWATCH        
(d)        None

19.   .......... is SAP super user for ABAP dictionary and software logistics functions in SAP Standard clients 000 and 001
(a) SAP*          
(b) DDIC           
(c) EARLYWATCH        
(d)        None

20.   .......... is the dialog user for support services in Client 066.
(a) SAP*          
(b) DDIC           
(c) EARLYWATCH        
(d)        None

21.   The eCATT .......... contain the commands to be executed during testing
(a) System Data Container         
(b) Test Data Container  
(c) Test Configuration    
(d) Test Script

22.   The eCATT ....... contains the other 3 objects in a eCATT and can be called for execution.
(a) System Data Container         
(b) Test Data Container
(c) Test Configuration    
(d) Test Script


23.   Transaction Codes, Table Names, Test Cases etc are examples of CATT ..........
(a) Editor Command      
(b) Function Code
(c) Object         
(d) Text

24.   A  ........ is used to distribute a change / development package to one or more systems.
(a) Delivery Route          
(b) Consolidation Route 
(c) Transport Layer        
(d) Domain Controller

25.   A ....... is used to identify in which SAP system the development was done and to determine the SAP systems to which the changes can be transported
(a) Delivery Route          
(b) Consolidation Route 
(c) Transport Layer        
(d) Domain Controller

26.   .......  is used to record and store all changes to SAP Customizing & Repository data
(a) SAP Delivery Route  
(b) SAP Transport Organizer      
(c) SAP Transport Layer
(d) SAP Domain Controller

27.   The user interface of the Transport Organizer is started by using Transaction Code ......
(a) SE01          
(b) SM01          
(c) ST01           
(d) SE07

28.   A  ........ is used for transporting changes done to customizing and repository data from one client/system to another client/system
(a) Transport Layer        
(b) Transport Request    
(c) Transport Route       
(d) Transport Domain Controller

29.   Changes to Customizing settings are recorded in ..............
(a) Workbench Requests           
(b) ABAP Requests       
(c) Customizing Requests          
(d) None

30.   .....  record changes made to ABAP Workbench objects and Cross Client Customizing.
(a) Workbench Requests           
(b) ABAP Requests
(c) Customizing Requests
(d) None     

1 comment:


  1. Thanks for sharing, nice post! Post really provice useful information!

    FadoExpress là một trong những top công ty chuyển phát nhanh quốc tế hàng đầu chuyên vận chuyển, chuyển phát nhanh siêu tốc đi khắp thế giới, nổi bật là dịch vụ gửi hàng đi nhậtgửi hàng đi pháp và dịch vụ chuyển phát nhanh đi hàn quốc uy tín, giá rẻ

    ReplyDelete