- Parametric – use per unit rate
- Estimate – from lowest to upper most level
- Indexing – use previous cost + 10 % increase
- Cost Capacity – Use previous project cost of different size
- Factoring – Use cost for an item from previous project
Contracting:
- Fixed Price
- Targeted Cost – include risk and uncertainties, benefit and risk are shared
- Maximum Guaranteed price – Risk to contractor, benefit is shared
- Easy Payback – cost and expenses reimbursed to contractor without profit
- Cost Plus – Time and materials are reimbursed with agreed profit margin
- Unit rate – based on work accomplished
Cost and Project Objectives:
- Cost is one of the project objectives
- Unless cost is controlled project objectives can be jeopardized
- Cost, time and quality are interlinked. Cost control is most critical
- Most poorly managed project have cost overrun
Cost Control:
Who control cost?
- Project manager must control spending and cost
- Strong culture of trust and responsibility is crucial for cost control
When to Control cost?
- Project cost spending is low at the beginning
- As project progress complexity increases and control effectiveness reduces
Where to control cost
- Cost are best controlled at source
- Issues and problems are to be resolved before cost is incurred
- Cost controller can be located on site
How to control Cost? – use traditional variance analysis and Earned Value Analysis
Cost Collection:
Labor
- Time sheet – normal delay in data collections and fed back to PM can cause be serious ( 3 weeks to reach PM)
Materials
- Accurate data must record procurement of materials at issue of PO, at receipt of goods and at payment of invoice
- Three stages collection gives more up to date indication on cost and spending information
Cost Codes
- Cost codes helps detailing spending and improves control
- Too much details can increase cost collections and slow action
Complete cost information data is mandatory for an effective cost control
SV = BCWP – BCWS
CV = BCWP - ACWP
Performance indices gives dimensionless index with value less or more than 1.0
CPI = BCWP / ACWP
Where CPI = cost performance index
SPI = BCWP/ BCWS
Where SPI = Schedule Performance index
Performance indicator:
CPI > 1.0 Project is saving
< 1.0 Project is over spending
SPI > 1.0 Project is ahead of schedule
< 1.0 project is behind schedule
- Accuracy of performance indicator is dependent on the accuracy of cost data collection
- Detailed data sheet indicating cost and schedule can be cumbersome and computer and software need to be utilized
- Usually used for large projects due to administrative costs
No comments:
Post a Comment